We, M Tower team are safely and steadily progressing well with the installation of façade glass curtain walls and chiller system at M Tower.
Construction is underway to meet our timeline for delivering.
Our partner, Min Dhama and its team are working on site safely under the prioritizing of safety, maintaining social-distancing measures and executing Covid 19 protocols.
A beacon along Yangon’s striking skyline, M Tower is soon to be completed its façade glass curtain wall installation in June.
Stay tuned for more updates!
Property and Asset Management Services by Jones Lang LaSalle.
The super structure steel erection work has been completed up to 8th Tier (21st Floor), all steel installations are scheduled to be completed by July 2020.
The remaining part of cantilever portion installation are still in progress. Slab concreting work completed up to 9th Floor and 10th floor re-bar installation and preparation works are still in progress.
All of the whole project construction and other works will be completed by July 2021.
Now, steel structure erection is almost completed 95 % and only remaining final tier installation for portion 2 (roof structure).
Currently, we are preparing to start ground floor construction and superstructure floor decking sheet laying.