Where We Are With Our Office Towers – May Work In Progress

M Tower

We, M Tower team are safely and steadily progressing well with the installation of façade glass curtain walls and chiller system at M Tower.

Construction is underway to meet our timeline for delivering.

Our partner, Min Dhama and its team are working on site safely under the prioritizing of safety, maintaining social-distancing measures and executing Covid 19 protocols.

A beacon along Yangon’s striking skyline, M Tower is soon to be completed its façade glass curtain wall installation in June.

Stay tuned for more updates!

Property and Asset Management Services by Jones Lang LaSalle.

Facade Lighting Installation
Main Chill Water Pipe Installation
South Elevation
Overview Stage of M Tower at Current Stage

Harbor Trade Tower

The super structure steel erection work has been completed up to 8th Tier (21st Floor), all steel installations are scheduled to be completed by July 2020. 

The remaining part of cantilever portion installation are still in progress. Slab concreting work completed up to 9th Floor and 10th floor re-bar installation and preparation works are still in progress.

All of the whole project construction and other works will be completed by July 2021.

Overall Steel Structure Installation
Casting Floor Concreting Work in Progress

HL Tower

Now, steel structure erection is almost completed 95 % and only remaining final tier installation for portion 2 (roof structure).

Currently, we are preparing to start ground floor construction and superstructure floor decking sheet laying.

Completed Steel Structure Installation
Steel Structure Installation in Progress
View from Pyay Road

30 May 2020